Business
Spain’s blackout changed the questions put to its grid
A year after the Iberian outage, the power system’s task was not only to generate cleaner electricity, but to carry and regulate it reliably.

The question raised by the Iberian blackout was not simply how much electricity Spain and Portugal could generate. It was whether the system could keep power flowing as conditions changed. A year after the outage of 28 April 2025, the Guardian reported on Spain’s continuing shift towards renewable generation and the grid changes being considered alongside it.
The European network operators’ final expert report described a sequence of interacting problems, including difficulties with voltage control and successive losses of generation. That matters because it rejects a simple story in which the presence of one type of power station explains everything. A network can have enough generating capacity on paper and still struggle to maintain voltage where it is needed.
The engineering question is partly about what grid operators buy and require as well as how much energy generators sell. Some equipment can support voltage or contribute to stability even when the amount of electricity it delivers is not especially large. Those services can be treated as an explicit part of operating a grid, rather than presumed to arrive automatically with every new power source.
Keeping the distinction in view also makes public debate more useful. The anniversary was an occasion to ask how the system is changing, not an argument for ending the shift to renewable power. The better test is whether the network, its operating rules and the equipment connected to it are being developed together, and whether the people responsible can see how the system behaves under stress.