Greenland

Greenland tells an oil explorer it cannot drill this winter

Nuuk says the proposed programme in Jameson Land cannot clear the required environmental and social checks in time.

Wind-shaped sandstone in Nunap Qeqqa, also known as Jameson Land, East Greenland.
Wind-shaped sandstone in Nunap Qeqqa, also known as Jameson Land, East Greenland.
Sources

Greenland’s government said on 12 August that White Flame Energy could not carry out its proposed drilling programme in Nunap Qeqqa, also known as Jameson Land, in the winter of 2026–27. Officials had already told the licence holder in July that its timetable was tight. Their published assessment went further: even if the company provided satisfactory documentation without any need for revisions, the approvals could not be finished before the proposed start.

The decision makes a practical distinction between holding an exploration licence and being authorised to carry out a specific operation. Greenland requires assessments of the environmental and social consequences alongside public consultation and other approvals. Preparations such as setting up a camp or bringing in drilling equipment cannot be treated separately as a way to get the programme under way before those decisions.

Officials had already intervened over equipment that was moved to Nerlerit Inaat without the necessary prior approvals. They did not require the material to be sent back. That handling of equipment already in transit was not approval to continue with it to the intended drilling area.

The government said it expected a revised timetable and remained in discussions with the company. It was still considering separate proposals, including for environmental baseline work. That leaves room for the project to move through the process without implying that permission for drilling has been granted or permanently ruled out. The immediate result is that the planned winter window is no longer available.