The EU’s border contract ends up in court

Europe’s troubled entry and exit system turns a familiar question about launch delays into a dispute about who should bear the cost.

The Berlaymont building, the European Commission’s headquarters in Brussels.
The Berlaymont building, the European Commission’s headquarters in Brussels.
Sources

A traveller waiting in an airport queue sees only the visible part of a border system. Behind it are computers, officials, local facilities and contracts that decide which organisation is responsible when the pieces do not come together. On 9 November reporting revealed that the EU agency responsible for a new entry and exit system had taken legal action against IBM, Atos and Leonardo over delays. The dispute does not establish liability; it raises the question of where liability falls.

The entry and exit system is meant to record movements across the external borders of participating European countries. The agency’s accounts connected its legal action to delays in delivery by the consortium. Airport complaints after the launch concerned a different, though related, question: whether the service available to passengers and officials operated reliably in use. A working product on one timetable is not necessarily a dependable service at a busy border post.

A customer commissioning public infrastructure can recover some losses through a contract if it has grounds to do so. That will not give back the time people have already spent waiting or tell a frontline officer how to respond on a busy day. The operational fix and the dispute over payment can proceed separately.

For future projects the lesson is to make the responsibility for both visible from the start. A deadline alone is not a definition of success. Public bodies also need a way to measure performance after launch and to know which problems the supplier, the agency and the local operator are expected to fix.